October 1, 2021 update: The new playground is now open!
The City of St. Albert is redeveloping Amherst Park playground in Akinsdale. Residents were invited to share feedback on the playground proposed design options through an online survey from April 28 - May 20, 2021.Feedback will help identify which play features are preferred and will be considered alongside:
Available budget
Sustainable maintenance requirements
Product availability
Project schedule
Contractor qualifications and experience
The scope of this program falls within the municipal repair, maintain, replace (RMR) capital plan. A guiding principle of this program is to replace "like for like" elements. Therefore, where possible the playground replacement design strives to include key play feature elements that are consistent with the original design.
We thank everyone who submitted their thoughts and ideas through the survey. Remember to click the subscribe button at the top right of this page to sign up for project updates.
October 1, 2021 update: The new playground is now open!
The City of St. Albert is redeveloping Amherst Park playground in Akinsdale. Residents were invited to share feedback on the playground proposed design options through an online survey from April 28 - May 20, 2021.Feedback will help identify which play features are preferred and will be considered alongside:
Available budget
Sustainable maintenance requirements
Product availability
Project schedule
Contractor qualifications and experience
The scope of this program falls within the municipal repair, maintain, replace (RMR) capital plan. A guiding principle of this program is to replace "like for like" elements. Therefore, where possible the playground replacement design strives to include key play feature elements that are consistent with the original design.
We thank everyone who submitted their thoughts and ideas through the survey. Remember to click the subscribe button at the top right of this page to sign up for project updates.
Share What We Heard Report & Final Playground Design on FacebookShare What We Heard Report & Final Playground Design on TwitterShare What We Heard Report & Final Playground Design on LinkedinEmail What We Heard Report & Final Playground Design link
Thank you to those who submitted their thoughts and ideas through the Amherst Park Playground survey. The valuable feedback and information that the project team received was used to select the successful playground contractor, MPI Inc.. The final Amherst Park playground design along with the results from the survey can be found in the What We Heard Report.
Construction on the park will begin in summer 2021.
Amherst Park Playground Replacement has finished this stage
Site assessment review and final scope requirement details are confirmed and finalized.
Public Engagement
Amherst Park Playground Replacement has finished this stage
Amherst Playground Replacement project is ready to receive public input on desired play feature preferences pertaining to the playground design proposal options received through the public tender process.
Survey Feedback Evaluation
Amherst Park Playground Replacement has finished this stage
Project team will evaluate feedback from the survey responses to help select the successful playground contractor and finalize the playground design.
Construction
Amherst Park Playground Replacement has finished this stage
Site work construction includes the removal and replacement of existing playground equipment, curbing, safety surfacing, and park furniture amenities.
Park Opening & Operation
Amherst Park Playground Replacement is currently at this stage
The park site is open to the public! Ongoing operations and maintenance is managed by the City.